amtico installed by lrs flooringAbindgon flooring installed by LRS FlooringLifestyle flooring installed by LRS FlooringDistinctive flooring installed by LRS FlooringCormar  flooring installed by LRS FlooringAlternative Flooring  flooring installed by LRS FlooringMohawk flooring installed by LRS FlooringPolyfloor flooring installed by LRS FlooringWoodward Grovesnor flooring installed by LRS Flooringkarndean flooring supplied by lrs flooring
certification
cscs certified

Method Statement

Reference No: 0012
Company: ISG PEARCE
Site Responsible Person: Lee Sanders
Tel. No: 0808 166 2175
Site Location: Netto Coventry Jubilee Crescent.
Names of Personnel on Site: Mark Fleetwood, Mark Reeves, Hugh Maguire & Richard Waters.
Start Date: 20th July 2011
Finish Date: 1 weeks from start date.

Brief Description of Work

Vinyl Installation

Vinyl works involving prepping sub floor. This includes clean & sweep making it ready for Latex screed. The following sequence of work applies:

  • Ensure adequate P.P.E for the job.
  • Application of damp proof membrane.
  • Application of Latex screed using an 110v mixer.
  • Glue out the floor with adhesive.
  • Fit Vinyl floor covering.
  • Weld joint with hot weld gun 110v.
  • Fit all skirting and diminishing strip with contact adhesive.

TILE INSTALLATION

  • Ensure adequate P.P.E for the job.
  • Grind out grout using a grinder fitted with dust vacuum attachment 110v.
  • Break out old tiles using a Kango 110v.
  • Reinstall new tiles with adhesive and grout.

Section 1 – GENERAL

SEQUENCE OF EVENTS / MODE OF OPERATION

Task No.DescriptionDayDateResponsible Person
1 Site inspection Day 1 19/07/2011 L.Sanders
2 Risk assessment Day 1 20/07/2011 M.Reeves
3 Material supply Day 2 20/07/2011 L.Sanders
4 Installation 1 weeks from start date 27/07/2011

methodology documentation